Renovation Experience

Follow Along With This

To Understand Timeline & General Expectations

Every renovation is different, but we can certainly learn a lot from previous projects. Follow along with this full kitchen remodel to see commonly asked questions and general expectations for the process.

The Kitchen Before

When these homeowners came to us they were tired of their 90’s remodeled kitchen that had a poor layout and disjointed design. The previous remodel converted a bedroom into the dining space, however, it wasn’t flowing with the adjacent spaces. The original stove and fridge were situated right next to each other. This meant tight quarters that bottlenecked their prep & cooking process.

After our initial consult, we assessed and measured the kitchen space and moved into design. Next steps included finalizing design selections, trades meeting, finalizing cabinet and fixtures orders, cleaning out the space, and starting demo. Visit our process page to learn more about these steps.

First Steps

Bumps Along The Road

Unfortunately, sometimes unexpected challenges present themselves during the process. For these homeowners, finding asbestos took the most patience during the process.

We uncovered asbestos flooring when we tore out the multiple layers of previous flooring. This added 2-3 weeks to the project due to having to find a remediation contractor on short notice. At that point, everything had been on track with no issues. Blue Terra handled it well, and the firm that did the work did a great job and was done in a day once they got us on their schedule.”

The homeowners decided to demo, paint, and finish trim so we set aside time in the project schedule for them to complete this work. Once demo was underway, we moved forward with our site work and sub-contractors. Below we outline the timeline of this project including the 2 week Asbestos setback.

All Hands on Deck

The Result

10 weeks later the kitchen was transformed and fully functional again. The lighting, artwork, and textiles helped hone in on the clients’ industrial craftsman style.

Clients’ Response to FAQs

Working on a smaller project?

Timeline: 3 weeks

Scope: Kitchen Countertop, Backsplash, Flooring, Lighting, Plumbing, Painting

For this kitchen refresh the clients wanted to keep their existing cabinets and appliances while upgrading the finishes and feel of the space. The clients came to us for design expertise on finishes and materials. In addition to our project coordination that ensured each step of the project ran efficiently and smoothly. The clients were able to continue to function in this space, being without a kitchen sink for just one day.

Working on a bigger project?

Timeline: 5 months

Scope: Full Kitchen, Dining, Laundry Room, Powder Room

An extensive design phase was needed to bring this 1901 farmhouse to the European inspired charmer it is today. We worked alongside additional contractors who rebuilt an exterior wall, updated the entire HVAC system, and installed all new windows. The clients also played a large role in coordination and demo as they worked to transform their entire property. After design, our site work encompassed about 3 weeks of the project. Including cabinet, countertop, and tile installation. We returned in the final stages to consult on the clients’ art collection and hang pieces that fit the new spaces.